Alert UPDATED - Street Maintenance Slurry & Striping Work - April 17-26 #malibu. Work cancelled April 16 due to weather. See updated schedule.

The City's paving contractor will begin Type II Slurry Seal work from April 15-19, and street striping will be conducted from April 22-26 on various City streets. Work hours are 7:00 AM to 5:00 PM and will include alternating lane closures, pilot cars, and traffic control when required.

Slurry Seal Schedule
Monday and Wednesday, April 15 & 17:
-- Malibu Road (PCH near Malibu Colony to 23900 block of Malibu Rd)
-- Carbon Cyn/Carbon Mesa (PCH to 22000 block of Carbon Mesa)

Thursday and Friday, April 18 & 19
-- Las Flores Cyn Rd (PCH to city limits)

Thursday, April 18
-- Roca Chica Dr (Seaboard Rd to cul-de-sac)
-- Seamoore Dr (Roca Chica Dr to cul-de-sac)

Friday, April 19
-- Royal Stone Dr (Roca Chica Dr to cul-de-sac)

Friday and Monday, April 19 & April 22
-- Seaboard Rd (Roca Chica Dr to 20400 block of Seaboard)

Monday, April 22
-- Piedra Chica (Big Rock to cul-de-sac)
-- Little Rock Way (all)
-- Pinnacle Way (all)
-- Cool Oak Way (all)
-- Rambla Vista (west entrance off PCH to Villa Costera)
-- Paseo Serra (Rambla Vista to cul-de-sac)

Striping Work
April 26-29 - view link below for streets scheduled for striping